  1. 90% Completed installation of steel beams on 2nd floor and roof level
  2. 90% completed installation of steel columns on 2nd floor and roof level
  3. 85% completed installation of steel deck on 1st floor level

Activities for coming weeks.

  1. Complete slab steel decking for 1st floor level.
  2. Installation of hydronic floor heating in 1st floor level.
  3. Install steel, form and pour concrete on 1st floor level slab.
  4. Complete installation of steel for 2nd & roof level.
  5. Start steel joist installation for 2nd and roof level