Alhamdolelah, we continue to make great progress towards the Rahmah Islamic Centre
! Here is a quick summary:
1. 85% completed backfilling around basement walls
2. 60% completed installation of steel and formwork on ground floor slab
3. 70% completed installation of steel staircase to basement
4. 90% completed installation of steel beams on 2nd floor and roof level
5. 90% completed installation of steel columns on 2nd floor and roof level
Attached is the full report.
Please continue to support the project by keeping RIC in your dua’s and donating towards the project in the link in our bio