RIC Construction Update

News & Updates
RIC Construction Update

RIC Construction Update

🚧

Alhamdolelah, we continue to make great progress towards the Rahmah Islamic Centre

🕌

! Here is a quick summary:

1. 50% completed backfilling of basement walls.

2. 100% completed waterproofing of basement wall

3. 25% Completed installation of steel beams on 2nd floor and roof level

4. 25% completed installation of steel columns on 2nd floor and roof level

Attached is the full report.

Please continue to support the project by keeping RIC in your dua’s and donating towards the project in the link in our bio!

Jazakom Allah Khairan

View Report

Become a Volunteer

'The best of people are those who are most beneficial to others' (Al-Mu'jam al-Awsat)
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Subscribe to our Newsletter

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.