Construction Update Report (Sept 30 to Oct 4, 2024)

News & Updates
Construction Update Report (Sept 30 to Oct 4, 2024)
  1. 100% completed installation of steel deck on ground floor level.
  2. 70% completed backfilling around basement walls.
  3. 25% completed installation of steel and formwork on ground floor slab.
  4. 90% completed installation of steel beams on 2nd floor and roof level.
  5. 90% completed installation of steel columns on 2nd floor and roof level.
Activities for coming weeks.
  1. Complete steel, form and pour concrete on ground floor level slab.
  2. Installation of hydronic floor heating in ground floor level.
  3. Complete installation of steel for 2nd & roof level.
  4. Start steel joist installation for 2nd and roof level.
View Report

Become a Volunteer

'The best of people are those who are most beneficial to others' (Al-Mu'jam al-Awsat)
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Subscribe to our Newsletter

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.